Respuesta :

Answer:

18 days

Step-by-step explanation:

M 8/ D 6 = M 24/ D 18

Answer:

2 days

Step-by-step explanation:

As it took 8 men 6 days, it would take 24 men 2 days. This is because there are 3 times the men, with the same amount of area to paint.