The COM 341 Medical Supplies is in charge of maintaining hospital supplies at UVic Hospital. The lead time for replenishment deliveries is 6 days. It was calculated that the mean demand for a 3-day period was 60 units, with a standard deviation of 7 units. Please assume that demand follows a normal distribution. COM 341 Medical Supplies would like to maintain a 90% service level.

Required:
What is the appropriate reorder point?