The delivered-equipment cost for a fully equipped CNC machining system is $4.2 million. The direct cost factor is 1.52 and the indirect cost factor is 0.37. Estimate the total plant cost if the indirect cost factor applies to the total direct cost. (Enter your answer in dollars and not in millions of dollars.) The total plant cost is $