Procurement costs such as costs of placing orders for materials and paying suppliers are usually classified as: Product-level costs. Output-unit-level costs. Vendor costs. Batch-level costs. Facility-level costs

Respuesta :

Answer:

Batch-level costs.

Explanation:

The procurement cost is the cost that incurred for placing the orders with respect to the materials and supplier payment and these cost would be classified as a batch level cost as these cost are incurred in the batches

So as per the given situation the batch level cost would be taken into the consideration

And, the other options are incorrect