It takes 2 workers 10 minutes to plant 3 trees. If all workers plant trees at the same constant rate, how many minutes will it take 4 workers to plant 24 trees?

Respuesta :

40

if it takes two workers 10 minutes to plant 3 trees,then it will take 4 workers 5 minutes to plant 3 trees.3÷24=8,then 5×8=40