To complete the first setup on a new machine took an employee 280 minutes. Using an 75​% cumulative average−time learning curve indicates that the second setup on the new machine is expected to take​ ________.

Respuesta :

Answer: 140 minutes

Explanation:

From the question, we are informed that to complete the first setup on a new machine took an employee 280 minutes. Using an 75​% cumulative average−time learning curve indicates that the second setup on the new machine is expected to take​:

We first multiply the 75​% cumulative average−time by the 280 minutes used. This will be:

= 280 × 75%

= 280 × 0.75

= 210

(280 + y)/2 = 210

280 + y = 210 × 2

280 + y = 420

y = 420 - 280

y = 140 minutes

A pattern in which the aggregate time per unit is lessened by a consistent rate each time the combined volume of parts produced is multiplied is called the cumulative average−time learning curve model.

The second setup on the new machine is expected to take 140 minutes.

This can be estimated by:

  • Time required by the employee for setting the first step = 280 minutes

  • According to the 75​% cumulative average−time learning curve:

[tex]=280 \times 75\%[/tex]

[tex]= 280 \times 0.75[/tex]

= 210

Let y = time required for the second setup then,

[tex]\dfrac{(280 + \text{y})}{2} = 210[/tex]

[tex]280 + \text{y} = 210 \times 2[/tex]

[tex]280 + \text{y} = 420[/tex]

[tex]\text{y} = 420 - 280[/tex]

[tex]\text{y} = 140\; \text{minutes}[/tex]

Therefore it will take 140 minutes for the second setup.