Need Help With This
*Please Show Work"

Answer:
Solution,
Time taken by 1 worker to complete the project= 2880 hours
Time taken by 12 workers to complete the project:
[tex] \frac{2880}{12} \\ = 480 \: hours[/tex]
Hope this helps ...
Good luck on your assignment...