Answer:
a) Identify which project should the company accept based on NPV method.
b) Identify which project should the company accept based on simple pay back method if the payback criteria is maximum 2 years.
c) Which project Giant Machinery should choose if two methods are in conflict.
Explanation:
Project 1 Project 2
Cost $175, 000 $185 ,000
Future Cash Flows
Year 1 $76,000 $83,000
Year 2 $67,000 $65,000
Year 3 $55,000 $87,000
Year 4 $78,000 $69,000
Year 5 $65,000 $57,000
NPV:
Project 1 = -175000 + 76000/1.09 + 67000/1.09² + 55000/1.09³ + 78000/1.09⁴ + 65000/1.09⁵ = $91,090
Project 2 = -185000 + 83000/1.09 + 65000/1.09² + 87000/1.09³ + 69000/1.09⁴ + 57000/1.09⁵ = $98,960
Payback:
Project 1 = -175000 - 76000 - 67000 = 32000 after 2 years, then 32000 / 55000 = 7 months
Project 2 = -185000 - 83000 - 65000 = 37000 after 2 years, then 37000 / 87000 = 5 months