Respuesta :
Answer:
1. Material Variances
Material Price Variance = $3,850 F
Material Quantity Variance = $5,200 U
2. Labor Variances
Labor Rate Variance = $1,350 U
Labor Efficiency Variance = $2,100 F
Explanation:
Calculation is as follows:
1. Material Variances
Material Price Variance = (Standard Price - Actual Price) x Actual units
Material Price Variance = ($2.60 - $2.4) x 19,250 pounds
Material Price Variance = $3,850 (favorable)
As the actual rate is less than standard rate the variance is favorable.
Standard Quantity = 2,500 x 6.9 = 17,250 pounds
Material Quantity Variance = (Standard Quantity - Actual Quantity) x Standard Rate
Material Quantity Variance = (17,250 - 19,250) x $2.60
Material Quantity Variance = $5,200 (Unfavorable)
As the actual raw material quantity used is higher than standard raw material quantity the variance is unfavorable.
2. Labor Variances
Actual Labor Rate = 4,500/450 = $10/hour
Labor Rate Variance = (Standard Rate - Actual Rate) x Actual Hours
Labor Rate Variance = ($7 - $10) x 450
Labor Rate Variance = $1,350 (Unfavorable)
As actual rate is higher than standard rate thus the variance is unfavorable.
Standard Hours = 2,500 x 0.3 = 750
Labor Efficiency Variance = (Standard Hours - Actual Hours) x Standard Rate
Labor Efficiency Variance = (750 - 450) x $7
Labor Efficiency Variance = $2,100 (Favorable)
As the Standard Hours is more than Actual Hours the variance is favorable.
Answer:
Check the explanation
Explanation:
Kindly check the attached image below to see the step by step explanation to the question above.