This exercise only contains parts b, c, d, e, and f.
Part 2
b) Given the demand, the cycle time for the production of the new train set =
30 seconds (round your response to one decimal place).
Part 3
c) The theoretical minimum number of workstationsequals
4 (round your response up to the next whole number).
Part 4
d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.)
Part 5Part 6Part 7Part 8Part 9
Task
Workstation #
A
Station 1
B
Station 2
C
Station 3
D
Station 3
E
Station 4
F
Station 5
Part 10
Were you able to assign all the tasks to the theoretical minimum number of workstations?
No
Part 11
e) The total idle time per cycle for the process =
30 seconds (enter your response as a whole number).
Part 12
f) The efficiency of the assembly line with 5 workstations =
80% (enter your response as a percentage rounded to one decimal place).
Part 13
If one used 6 workstations instead of 5, the efficiency of the assembly line would be =
enter your response here% (enter your response as a percentage rounded to one decimal place).