The following clause is included in a contract: "THE CONTRACTOR IS NOT RESPONSIBLE FOR DELAYS CAUSED BY WEATHER, EARTHQUAKES, FLOODS, OR OTHER ACTS OF GOD." This clause would limit the contractor's liability for delays caused by ________.
1) Weather
2) Earthquakes
3) Floods
4) Acts of God