1. Refer to the table below. What is the cumulative budgeted cost at the end of week 8? Amounts are in thousands of Rand.
(6 marks)
WEEK
TBC 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Conception + Scheduling 360 300 60
Design ERD 316 144 172
Programming 1728 168 168 168 168 168 168 168 168 168 168 48
Database 226 25 105 96
Adjustment + Redesigning 432 24 24 144 168 72
Closeout 96 96
Total 3158 300 204 365 273 288 192 168 168 168 168 168 168 192 168 168
CBC